    Norway and Oakdale Hydroelectric Dams FERC Licensing Process Timeline

    Progress Reports
    Filing Date: April 9, 2002; October 9, 2002; April 9, 2003; October 9, 2003; April 9, 2004

    Preconsultation Studies
    Completion Date: November 9, 2001

    First Stage Consultation Package
    Completion Date: January 31, 2002

    Exhibit E, Environmental Report
    Completion Date: August 23, 2003

    Exhibits A-G, Engineering Studies
    Completion Date: May 30, 2003

    Supporting Design Report
    Completion Date: March 28, 2003

    Water Quality Certification Application
    Completion Date: January 2, 2004

    License Application
    Completion Date: June 25, 2004